Critical path in CPM is the path having

Construction ManagementOriginal practiceMEDIUM

Choose the correct answer

A

Maximum duration through the network

B

Zero activities

C

Minimum cost only

D

Minimum number of activities

Correct Answer

A. Maximum duration through the network

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Critical path controls project completion time and has zero total float.