Critical path in CPM is the path having
Construction ManagementOriginal practiceMEDIUM
Choose the correct answer
A
Maximum duration through the network
B
Zero activities
C
Minimum cost only
D
Minimum number of activities
Correct Answer
A. Maximum duration through the network
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Critical path controls project completion time and has zero total float.