Crashing a project network means:
Construction ManagementConstruction Materials, Practices, Planning and ManagementHARD
Choose the correct answer
A
reducing project duration by spending extra resources on critical activities
B
delaying noncritical activities only
C
removing all dummy activities
D
using only optimistic time
Correct Answer
A. reducing project duration by spending extra resources on critical activities
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Crashing shortens duration, usually at increased direct cost, and is effective when applied to critical activities.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.