Civil Engineering MCQJE Level Civil Engineering

Cost plus percentage contract tends to give contractor:

Construction ManagementEstimating, Costing and Construction ManagementMEDIUM

Choose the correct answer

A

Fixed item rate only

B

No reimbursement of cost

C

Maximum incentive to save cost

D

Little incentive to reduce cost

Correct Answer

D. Little incentive to reduce cost

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Profit increases with cost, so economy incentive is weak.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.