An S-curve in project management is used to plot:

Construction ManagementS-CurveHARD

Choose the correct answer

A

Resource usage per time period (resource histogram)

B

Cumulative planned and actual cost or work progress versus time

C

Float variation of critical activities over the project

D

Number of activities completed vs number scheduled per period

Correct Answer

B. Cumulative planned and actual cost or work progress versus time

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

S-curve: Y = cumulative cost/progress, X = time. Shape is S-shaped: slow start (mobilisation), rapid build-up (peak construction), slowdown (commissioning/closeout). Used to compare planned S-curve vs actual S-curve: gap below = behind schedule/under-spend; gap above = over-spend. Essential for project tracking and cash flow forecasting.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap