A resource histogram in project management displays:

Construction ManagementProject ManagementMEDIUM

Choose the correct answer

A

The sequence of activities along the critical path

B

The number of resources required in each time period

C

Cumulative cost expenditure over the project duration

D

Float available for each activity in the network

Correct Answer

B. The number of resources required in each time period

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Resource histogram: X-axis = time periods (days/weeks), Y-axis = resource quantity needed. Peaks indicate crunch periods. Used for resource planning, identifying when to hire/release workers, and as input to resource leveling. When area under histogram = total man-days needed for project.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account