A dummy activity in an AOA (activity-on-arrow) CPM network is used to:

Construction ManagementDummy ActivityMEDIUM

Choose the correct answer

A

Represent an activity with zero cost but positive duration

B

Maintain logical dependency where two activities share the same start and end nodes

C

Identify activities that are not on the critical path

D

Represent activities with 100% float

Correct Answer

B. Maintain logical dependency where two activities share the same start and end nodes

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Dummy activities have zero duration and zero resources — they only show logical dependency. Used when: (1) two parallel activities share the same tail and head nodes (would create duplicate arrows), or (2) one activity's start depends on only part of a preceding set. Dummies appear as dashed arrows in AOA diagrams.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account