A dummy activity:

Construction ManagementConstruction ManagementMEDIUM

Choose the correct answer

A

has no tail event but had only a head event

B

had only a head event but no tail event

C

does not require any resource nor any time

D

had no sequence and can be fitted anywhere

Correct Answer

C. does not require any resource nor any time

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

A dummy activity has zero duration and zero resource requirement, used only to maintain logical dependency

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to WBPSC AE Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account