Civil Engineering MCQJE Level Civil Engineering

A design assistant has to decide on probabilistic activity duration. Which statement is sound? Avoid the common trap that pERT uses only one fixed duration.

Construction ManagementPERTMEDIUM

Choose the correct answer

A

expected time is commonly based on optimistic, most likely and pessimistic estimates

B

PERT is a soil test

C

PERT uses only one fixed duration

D

pessimistic time is ignored

Correct Answer

A. expected time is commonly based on optimistic, most likely and pessimistic estimates

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PERT handles uncertainty in activity durations. Correct option: A.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account