A design assistant has to decide on probabilistic activity duration. Which statement is sound? Avoid the common trap that pERT uses only one fixed duration.
Construction ManagementPERTMEDIUM
Choose the correct answer
A
expected time is commonly based on optimistic, most likely and pessimistic estimates
B
PERT is a soil test
C
PERT uses only one fixed duration
D
pessimistic time is ignored
Correct Answer
A. expected time is commonly based on optimistic, most likely and pessimistic estimates
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
PERT handles uncertainty in activity durations. Correct option: A.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.