A design assistant has to decide on deterministic project scheduling. Which statement is sound? Avoid the common trap that float is measured only in rupees.
Construction ManagementCPMEASY
Choose the correct answer
A
critical path has zero total float in the basic network
B
CPM ignores activity durations
C
float is measured only in rupees
D
critical path is always the shortest path
Correct Answer
A. critical path has zero total float in the basic network
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
CPM identifies activities controlling project duration. Correct option: A.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.