A critical path in project management has
Construction ManagementConstruction ManagementMEDIUM
Choose the correct answer
A
zero slack
B
minimum slack
C
maximum slack
D
infinite slack
Correct Answer
B. minimum slack
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Critical-path activities have minimum (zero) slack/float.