Civil Engineering MCQJE Level Civil Engineering

A candidate is comparing options for Development Length. Which line correctly handles anchorage of reinforcing bars? Avoid the common trap that it is the clear cover to the bar.

RCCDevelopment LengthEASY

Choose the correct answer

A

it equals stirrup spacing

B

it is the clear cover to the bar

C

it is the unsupported length of column

D

it is the embedment length needed to develop design stress in the bar

Correct Answer

D. it is the embedment length needed to develop design stress in the bar

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Development length ensures bond transfer from steel to concrete. Correct option: D.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account