A bulldozer pushes material over a 100 m distance at 1.5 km/hr and returns at 3.0 km/hr. Neglecting fixed delays, the number of productive cycles per hour is approximately:

Construction ManagementConstruction EquipmentMEDIUM

Choose the correct answer

A

5

B

8

C

10

D

15

Correct Answer

C. 10

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Push time = 100m ÷ 1500 m/hr = 0.0667 hr = 4 min. Return time = 100m ÷ 3000 m/hr = 0.0333 hr = 2 min. Cycle time = 4 + 2 = 6 min. Cycles/hr = 60/6 = 10. In practice, efficiency factor (≈0.83) reduces this to ~8.3 productive cycles.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account