A bulldozer makes 10 cycles per hour, blade capacity 4 m³ (loose measure), operating 8 hours per day. The daily output in loose measure is:

Construction ManagementEquipment OutputMEDIUM

Choose the correct answer

A

200 m³/day

B

320 m³/day

C

400 m³/day

D

500 m³/day

Correct Answer

B. 320 m³/day

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Output per hour = cycles/hr × blade capacity = 10 × 4 = 40 m³/hr (loose). Daily output = 40 × 8 = 320 m³/day (loose). To convert to bank measure: divide by swell factor (typically 1.15–1.30 for soil). This loose measure figure is used for truck sizing and haul road planning.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account