Civil Engineering MCQJE Level Civil Engineering
Which of the following statements about recording executed quantities is technically sound?
Estimation and CostingMeasurement BookHARD
Choose the correct answer
A
it records only weather
B
measurements should be recorded clearly for billing and audit
C
measurement book is optional for all public works
D
it replaces specifications
Correct Answer
B. measurements should be recorded clearly for billing and audit
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
MB entries support payment and verification. Correct option: B.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.