Civil Engineering MCQAE Level Civil Engineering
Which of the following about recording executed quantities in civil engineering is correct?
Estimation and CostingMeasurement BookHARD
Choose the correct answer
A
it replaces specifications
B
measurement book is optional for all public works
C
it records only weather
D
measurements should be recorded clearly for billing and audit
Correct Answer
D. measurements should be recorded clearly for billing and audit
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
MB entries support payment and verification. Correct option: D.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.