Civil Engineering MCQJE Level Civil Engineering
When the problem statement highlights two columns close to each other or near property line, which response is technically correct? Avoid the common trap that it is never reinforced.
Foundation EngineeringCombined FootingEASY
Choose the correct answer
A
it is never reinforced
B
it eliminates soil pressure
C
it is used only for water tanks
D
it is used when isolated footings overlap or eccentricity must be controlled
Correct Answer
D. it is used when isolated footings overlap or eccentricity must be controlled
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Combined footings help align resultant load with footing centroid. Correct option: D.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.