Civil Engineering MCQJE Level Civil Engineering
When the problem statement highlights earthwork costing, which response is technically correct? Avoid the common trap that both are ignored in earthwork rates.
Estimation and CostingLead and LiftEASY
Choose the correct answer
A
both are ignored in earthwork rates
B
lift is aggregate size
C
lead is cement setting time
D
lead is horizontal transport distance and lift is vertical raising distance
Correct Answer
D. lead is horizontal transport distance and lift is vertical raising distance
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Earthwork rates depend on transport and vertical movement. Correct option: D.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.