Civil Engineering MCQAE Level Civil Engineering

When setting out the foundation of a building from structural drawings, the first step is to:

SurveyingSetting Out BuildingMEDIUM

Choose the correct answer

A

Excavate the foundation immediately

B

Establish a reference point (benchmark) and transfer the building grid to the ground using pegs and a theodolite or total station, checking squareness by measuring diagonals

C

Lay PCC without marking

D

Install formwork directly

Correct Answer

B. Establish a reference point (benchmark) and transfer the building grid to the ground using pegs and a theodolite or total station, checking squareness by measuring diagonals

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Setting out sequence: (1) Establish site TBM from nearest GTS BM; (2) Lay out base line parallel to road/boundary; (3) Mark grid points using theodolite/total station; (4) Check squareness (diagonals should be equal for rectangle); (5) Offset pegs for trench edges; (6) Mark depths using batter boards/sight rails.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account