Vertical formwork to columns, walls and beams may generally be removed after:

Concrete Technology & RCCRemovalMEDIUM

Choose the correct answer

A

7 days

B

16 to 24 hours

C

21 days

D

3 days

Correct Answer

B. 16 to 24 hours

Why is this the answer?

IS 456 gives typical minimum stripping time for vertical formwork as 16-24 hours. Reference: Clause 11.3; Table 11 | Page: verify from your official BIS copy/PDF pagination