Civil Engineering MCQAE Level Civil Engineering
To prevent the sloughing of an earthen dam, it is necessary to provide
Irrigation EngineeringIrrigation EngineeringMEDIUM
Choose the correct answer
A
riprap
B
impervious blanket
C
rock toe
D
relief wells
Correct Answer
C. rock toe
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Rock toe protects against sloughing and supports downstream slope of earth dam.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to WBPSC AE Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.