Civil Engineering MCQAE Level Civil Engineering

The slump test (IS 1199) for concrete workability is NOT suitable for:

Building MaterialsConcrete Slump TestMEDIUM

Choose the correct answer

A

Low workability concrete (slump 10-40 mm)

B

Medium workability concrete

C

Very stiff or very lean mixes with near-zero slump, for which the Vee-Bee test is more appropriate

D

High slump concrete (>100 mm)

Correct Answer

C. Very stiff or very lean mixes with near-zero slump, for which the Vee-Bee test is more appropriate

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Slump test range: 25-125 mm (meaningful). For stiff concrete (Vee-Bee time > 10 s) or dry mixes: Vee-Bee consistometer test. For high workability/SCC: slump flow test. Compaction factor test: measures workability by ratio of compacted to fully compacted concrete weight.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.