Civil Engineering MCQJE Level Civil Engineering

The 'reservoir routing' method (Puls method / level pool routing) solves for:

HydrologyHydrologyMEDIUM

Choose the correct answer

A

Flow velocity profile in river cross-section

B

Outflow hydrograph from a reservoir given inflow, using continuity equation and storage-outflow-elevation relationship

C

Sediment trap efficiency in reservoir

D

Evaporation from reservoir surface

Correct Answer

B. Outflow hydrograph from a reservoir given inflow, using continuity equation and storage-outflow-elevation relationship

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Level-pool (Puls) routing: reservoir has horizontal water surface (level pool). Given inflow hydrograph I(t): solve storage-outflow continuity equation S + O×Δt/2 = S_prev + (I_prev+I)×Δt/2 − O_prev×Δt/2. Storage-outflow-elevation relationship (S−O curve) pre-computed. At each time step: find outflow O and storage S. Gives outflow hydrograph from reservoir (attenuated peak, delayed timing).

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account