Civil Engineering MCQAE Level Civil Engineering

The pond level in a weir/barrage is the:

Irrigation EngineeringWeir Pond LevelMEDIUM

Choose the correct answer

A

Maximum flood level upstream

B

Designed full supply level of the canal just upstream of the weir, from which canals draw their supply

C

Minimum operating level

D

Level at which the weir overflows

Correct Answer

B. Designed full supply level of the canal just upstream of the weir, from which canals draw their supply

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Pond level = Full Supply Level (FSL) at the head of the off-taking canals = designed upstream HFL above which canals can draw their design discharge. The weir crest is set to maintain this level under design discharge conditions (gross command consideration).

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap