Civil Engineering MCQJE Level Civil Engineering
The pitch of bolts is the distance between centres of two consecutive bolts measured:
Steel StructuresRCC, Steel and Timber StructuresHARD
Choose the correct answer
A
along the line of force
B
along weld throat
C
perpendicular to line of force
D
through plate thickness
Correct Answer
A. along the line of force
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Pitch is centre-to-centre spacing of bolts in the direction of the line of force.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.