Civil Engineering MCQJE Level Civil Engineering

The 'observational method' in geotechnical engineering (Peck, 1969) involves:

Soil MechanicsSoil MechanicsHARD

Choose the correct answer

A

Using maximum possible loads for design (no flexibility)

B

Design-as-you-go: construct incrementally monitoring actual behaviour; pre-planned contingencies if limits exceeded

C

Using only laboratory test results without field verification

D

Random design without any monitoring

Correct Answer

B. Design-as-you-go: construct incrementally monitoring actual behaviour; pre-planned contingencies if limits exceeded

Why is this the answer?

Observational method: (1) Design on best estimate of properties; (2) Define acceptable limits; (3) Select monitoring scheme; (4) Plan contingency measures; (5) Monitor during construction; (6) Modify design if needed. Particularly suitable when: soil variability high, properties uncertain, failure mode well-defined. Examples: embankment on soft clay with pore pressure monitoring, piled foundation monitoring. Avoids: over-conservative design AND unexpected failure.

Related Soil Mechanics MCQs

More solved Soil Mechanics questions for AE/JE Civil Engineering exams.

View all Soil Mechanics MCQs →

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account