Civil Engineering MCQJE Level Civil Engineering

The 'grouting' method used to fill large voids in karstic limestone is:

Soil MechanicsSoil MechanicsMEDIUM

Choose the correct answer

A

Compaction grouting (too viscous for large voids)

B

Bulk (filling) grouting — cement-bentonite slurry poured or pumped into large karstic voids and mine workings

C

Chemical grouting with silicates only

D

Electro-osmosis (for cohesive soils only)

Correct Answer

B. Bulk (filling) grouting — cement-bentonite slurry poured or pumped into large karstic voids and mine workings

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Types of grouting: (1) Permeation (chemical) grouting: low-viscosity chemicals (sodium silicate, acrylate) for fine sands; (2) Compaction grouting: stiff grout densifies loose soil; (3) Jet grouting: high-pressure jet cuts soil + grout forms column; (4) Bulk/filling grouting: cement-bentonite slurry poured into large voids (karst caves, old mine workings, tunnels). Karst voids: drilling + gravity/low-pressure cement filling.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.