Civil Engineering MCQAE Level Civil Engineering

The effective green time per phase at a signalized intersection is the actual green time plus:

Transportation EngineeringSignalized Intersection DelayMEDIUM

Choose the correct answer

A

Red time only

B

Yellow time only

C

All-red time only

D

A portion of yellow (amber) time minus the start-up lost time

Correct Answer

D. A portion of yellow (amber) time minus the start-up lost time

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Effective green = actual green time + yellow time - lost time. In Webster method: effective green = actual green + amber - start-up loss (typically 2 s each component). Effective green is used in capacity calculation: capacity = s x g/C.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account