The design flood used for spillway capacity of a major dam is generally:

Irrigation EngineeringSpillway Design FloodMEDIUM

Choose the correct answer

A

Mean annual flood

B

50-year return period flood

C

Standard Project Flood (SPF) or Probable Maximum Flood (PMF) based on dam hazard potential

D

10-year return period flood

Correct Answer

C. Standard Project Flood (SPF) or Probable Maximum Flood (PMF) based on dam hazard potential

Why is this the answer?

IS 11223 and CWC guidelines: Spillway design flood for small dams (low hazard) = 100-year flood; medium dams = SPF (Standard Project Flood, approximately 40-50% of PMF); large dams/high hazard = PMF (Probable Maximum Flood). PMF uses the Probable Maximum Precipitation (PMP).

Related Irrigation Engineering MCQs

More solved Irrigation Engineering questions for AE/JE Civil Engineering exams.

View all Irrigation Engineering MCQs →

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account