Civil Engineering MCQJE Level Civil Engineering

The 'command area development' (CAD) programme under irrigation projects aims to:

Irrigation EngineeringIrrigation EngineeringMEDIUM

Choose the correct answer

A

Only construction of main canals

B

Bridge gap between potential created by dams/canals and actual utilisation by developing field channels, levelling, and on-farm works

C

Only study water quality

D

Dam safety inspection only

Correct Answer

B. Bridge gap between potential created by dams/canals and actual utilisation by developing field channels, levelling, and on-farm works

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

CAD programme: ensures irrigation potential created by dam/canal is actually UTILISED. Activities: field channels (watercourses), land levelling, consolidation, on-farm development (OFD), lining of watercourses, drainage. Without CAD: gap between irrigation potential created and actually utilised remains. Government provides subsidies for OFD works.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account