The capacity of a group of piles driven in clay is:

Foundation EngineeringFoundation EngineeringMEDIUM

Choose the correct answer

A

equal to single pile capacity

B

less than that of pile capacity

C

greater than that of pile capacity

D

multiplied by number of piles

Correct Answer

B. less than that of pile capacity

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

In clay, group efficiency can be less than one due to overlapping stress zones and block failure