The canal has to irrigate 12000 ha of rice with duty 1000 ha/cumec. Capacity factor is 0.8 and time factor 0.75. Required discharge is
Irrigation EngineeringIrrigation EngineeringMEDIUM
Choose the correct answer
A
96 m³/s
B
9 m³/s
C
20 m³/s
D
12.8 m³/s
Correct Answer
C. 20 m³/s
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Q = area/(duty × capacity factor × time factor)=12000/(1000×0.8×0.75)=20 m³/s