The approximate volume of one 50 kg bag of cement is:

Estimation and CostingEstimating, Costing and Construction ManagementEASY

Choose the correct answer

A

0.1000 cubic metre

B

0.0100 cubic metre

C

0.0347 cubic metre

D

0.5000 cubic metre

Correct Answer

C. 0.0347 cubic metre

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

With specific gravity about 3.15, one 50 kg cement bag occupies about 0.0347 cubic metre.