Survey camp problem: For crop delta 75 cm and base period 150 days, duty is approximately:

Fluid MechanicsHydraulics, Hydrology and IrrigationHARD

Choose the correct answer

A

1728 ha/cumec

B

17.3 ha/cumec

C

13 ha/cumec

D

432 ha/cumec

Correct Answer

A. 1728 ha/cumec

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Duty D = 864 B / Delta when Delta is in cm.