Soffit formwork to slabs, with props left under, may generally be removed after:

Concrete Technology & RCCRemovalMEDIUM

Choose the correct answer

A

21 days

B

3 days

C

16 hours

D

7 days

Correct Answer

B. 3 days

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Typical minimum stripping time for slab soffit formwork with props left is 3 days. Reference: Clause 11.3; Table 11 | Page: verify from your official BIS copy/PDF pagination