Civil Engineering MCQJE Level Civil Engineering
Regarding item rate contract, choose the correct option.
Environmental EngineeringEnvironmental Engineering, Estimation, Contracts and EquipmentMEDIUM
Choose the correct answer
A
labour supply only
B
cost plus percentage only
C
lump sum with no item rate
D
contract where contractor quotes rate for each item
Correct Answer
D. contract where contractor quotes rate for each item
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
contract where contractor quotes rate for each item is the correct association for item rate contract.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.