Civil Engineering MCQJE Level Civil Engineering

Practical application: Earthwork excavation for a trench 15 m long, 3 m wide and 1 m deep is:

Environmental EngineeringEnvironmental Engineering, Estimation, Contracts and EquipmentMEDIUM

Choose the correct answer

A

0+2

B

22.5 m³

C

45 m³

D

19 m³

Correct Answer

C. 45 m³

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Earthwork quantity = length x width x depth.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.