Pavement field check: In levelling, RL of BM is 120 m, BS = 1.82 m and FS = 0.92 m. RL of next point is:

SurveyingSurveying and GeomaticsHARD

Choose the correct answer

A

120.9 m

B

119.1 m

C

122.74 m

D

117.26 m

Correct Answer

A. 120.9 m

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

RL of next point = RL of BM + BS - FS.