Minimum number of days after which formwork including props under the soffits of beams can be removed is:

Building MaterialsBuilding MaterialsMEDIUM

Choose the correct answer

A

14

B

10

C

7

D

21

Correct Answer

A. 14

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

For beam soffits with props, the normal minimum removal period is 14 days