Civil Engineering MCQAE Level Civil Engineering
Minimum number of days after which formwork including props under the soffits of beams can be removed is:
Building MaterialsBuilding MaterialsMEDIUM
Choose the correct answer
A
14
B
10
C
7
D
21
Correct Answer
A. 14
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
For beam soffits with props, the normal minimum removal period is 14 days