Minimum curing period for ordinary Portland cement concrete is generally:

Concrete Technology & RCCCuringMEDIUM

Choose the correct answer

A

7 days

B

1 day

C

28 days

D

3 days

Correct Answer

A. 7 days

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

IS 456 specifies a minimum curing period of 7 days for OPC concrete under ordinary conditions. Reference: Clause 13.5.1 | Page: verify from your official BIS copy/PDF pagination