Civil Engineering MCQAE Level Civil Engineering

Lacey's silt factor is written as

Irrigation EngineeringIrrigation EngineeringMEDIUM

Choose the correct answer

A

f = 1.75 (d_m)^(1/2)

B

f = 0.01 (d_mm)^(2/3)

C

f = 4.75 (d_mm)^(1/6)

D

f = 1.76 (d_mm)^(1/2)

Correct Answer

D. f = 1.76 (d_mm)^(1/2)

Why is this the answer?

Lacey's silt factor f = 1.76 √(d_mm), where d_mm is the mean particle size in mm.