Inspection scenario: Earthwork excavation for a trench 20 m long, 1.5 m wide and 1.2 m deep is:
Environmental EngineeringEnvironmental Engineering, Estimation, Contracts and EquipmentHARD
Choose the correct answer
A
36 m³
B
18 m³
C
30 m³
D
22.7 m³
Correct Answer
A. 36 m³
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Earthwork quantity = length x width x depth.