In the sand replacement method (IS 2720 Part 28) for field density determination, the volume of the excavated hole is found by:

Soil MechanicsField Density Sand ReplacementMEDIUM

Choose the correct answer

A

Measuring the diameter and depth of the hole

B

Using a graduated cylinder of water

C

The volume of calibrating sand poured into the hole minus cone volume

D

The weight of soil removed divided by unit weight

Correct Answer

C. The volume of calibrating sand poured into the hole minus cone volume

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

In sand replacement method: Standard sand of known density is poured into the hole via a sand cone device. Volume of hole = (weight of sand in hole) / (density of calibrating sand). Cone volume is determined separately.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account