In post-tensioning, grouting of ducts is done mainly to

Steel StructuresGeneralMEDIUM

Choose the correct answer

A

protect tendons and improve bond

B

increase water-cement ratio

C

reduce concrete grade

D

make tendons removable always

Correct Answer

A. protect tendons and improve bond

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Grout provides corrosion protection and bond between tendon and concrete.