A

Wc = 4Mp/L

B

Wc = 6Mp/L

C

Wc = 8Mp/L

D

Wc = 2Mp/L

Correct Answer

B. Wc = 6Mp/L

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Propped cantilever: plastic hinges form at fixed end and at load point (2 hinges for mechanism in 1-degree indeterminate structure). Using virtual work: Wc × δ = Mp × (θ + 2θ) = 3Mpθ and δ = L/2 × θ. So Wc = 3Mp/(L/2) = 6Mp/L. Plastic moment Mp = Zp × fy (Zp = plastic section modulus).

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account