Civil Engineering MCQAE Level Civil Engineering
In Francis equation for necessary correction for end contraction for calculation of discharge capacity of the spillway of a dam, n represents:
Irrigation EngineeringIrrigation EngineeringMEDIUM
Choose the correct answer
A
No. of piers
B
No. of deflecting corners
C
No. of opening in the spillway
D
No. of gates
Correct Answer
B. No. of deflecting corners