In earthwork measurement, the prismoidal formula is more accurate because it uses:
Estimation and CostingHighway Engineering, Estimating, Costing and ContractsHARD
Choose the correct answer
A
only first area
B
only lead
C
only average depth at one point
D
end areas and mid-area
Correct Answer
D. end areas and mid-area
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Prismoidal formula accounts for mid-section area and changing ground profile.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.