In earthwork for roads and canals, the term 'lift' is defined as:

Estimation and CostingEarthworkHARD

Choose the correct answer

A

Horizontal distance over which excavated material is transported

B

Vertical height through which excavated material is raised above the excavation level

C

Volume of soil after compaction per unit volume in bank condition

D

Factor by which embankment volume exceeds cut volume

Correct Answer

B. Vertical height through which excavated material is raised above the excavation level

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Lead = horizontal transport distance (base distance for carriage). Lift = vertical height of raising (charged separately at higher rate). Standard lead is 30 m and standard lift is 1.5 m as per Schedule of Rates; beyond these limits, extra payment applies.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account