Civil Engineering MCQJE Level Civil Engineering
In contract estimating, a prime cost item is best understood as:
Estimation and CostingPrime Cost ItemMEDIUM
Choose the correct answer
A
An allowance for a specified item whose exact cost is to be settled later
B
The contractor's total profit on the work
C
The measured volume of earthwork
D
A deduction for every door opening
Correct Answer
A. An allowance for a specified item whose exact cost is to be settled later
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Prime cost items are allowances included when exact supply cost is not finalized at tender stage.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap