In an initial (routine) pile load test as per IS 2911 Part 4, the safe load on a single pile is taken as the lesser of:

Foundation EngineeringPile Load Test InterpretationMEDIUM

Choose the correct answer

A

The failure load and the load at 25 mm settlement

B

Two-thirds of the final load at which the total settlement exceeds 12 mm, and half the load at which the total settlement equals 10% of the pile diameter

C

The test load divided by 3 (FOS = 3 always)

D

The load at which the rate of settlement stabilises

Correct Answer

B. Two-thirds of the final load at which the total settlement exceeds 12 mm, and half the load at which the total settlement equals 10% of the pile diameter

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

IS 2911 Part 4: Safe load = lesser of: (a) 2/3 of final load causing total settlement = 12 mm (or 10% of pile diameter, whichever is less) and (b) 50% of final load causing total settlement equal to 10% of pile diameter. Alternatively, FOS = 2.5 on ultimate load from load-settlement curve. Maintain each load increment for 24 h.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account