If time factor Tv = 0.197, drainage path Hdr = 3 m and Cv = 1 x 10^-7 m2/s, time is:
Soil MechanicsSoil Mechanics and Foundation EngineeringHARD
Choose the correct answer
A
3.00 x 10^7 s
B
1.97 x 10^6 s
C
5.91 x 10^6 s
D
1.773 x 10^7 s
Correct Answer
D. 1.773 x 10^7 s
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
t = Tv Hdr^2/Cv = 0.197 x 9/1e-7 = 1.773e7 s.