If time factor Tv = 0.197, drainage path Hdr = 3 m and Cv = 1 x 10^-7 m2/s, time is:

Soil MechanicsSoil Mechanics and Foundation EngineeringHARD

Choose the correct answer

A

3.00 x 10^7 s

B

1.97 x 10^6 s

C

5.91 x 10^6 s

D

1.773 x 10^7 s

Correct Answer

D. 1.773 x 10^7 s

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

t = Tv Hdr^2/Cv = 0.197 x 9/1e-7 = 1.773e7 s.